Winter Construction Operations – i80 Update – February 4th

Weekly Update: February 4, 2019

Dear Stakeholder,

Winter Construction Operations

Northern Nevada weather changes day-to-day, sometimes by the hour.  Most construction operations and schedules are dependent on the weather for the safety of workers and drivers. The I-80 project team is working on pedestrian improvements on Keystone Ave. and north McCarran Blvd. under I-80. New accessible pedestrian ramps will be constructed in the coming months as weather temperatures increase and precipitation decreases. Pedestrian detours and minor single lane closures will be in place on Keystone Ave. and north McCarran Blvd.

Week of February 4, 2019

  • Pedestrian detour and minor single lane closures on Keystone Avenue between West 5th Street and West 7th Street, weather permitting.
  • I-80 eastbound truck parking at Mogul is closed for the immediate future.
  • Lane shifts with flagger-controlled traffic at Stoker Avenue and West 4th Street.
  • Intermittent daytime lane, ramp and shoulder reductions on I-80 westbound between Keystone Ave. and the California/Nevada stateline.