NDOT I-80 WEST OF RENO: August 3, 2018 Traffic Control Update

Dear Stakeholder:

Construction activities are shut down during Hot August Nights, August 6 to 12. Visit Hot August Nights for a complete list of event details. Construction will resume the evening of August 13. Crews will continue paving operations on I-80 west from Robb Drive to Mogul when construction resumes the evening of August 13.

Week of August 13, 2018

  • Mainline paving continues
  • Night time paving on I-80 westbound from Keystone Ave. to Robb Drive.  At least one lane of traffic will be maintained at all times.
  • Intermittent night time ramp closures on I-80 westbound between Robb Drive and 4th Street from 9 pm to 5 am. No two consecutive ramps will be closed at the same time.
  • I-80 eastbound and westbound overnight lane closures weekdays 7 pm to 7 am.
  • Daytime shoulder closures on I-80 westbound from Keystone Ave. to Mogul.
Contractor paves deep pavement sections near bridge approaches. Roadways adjacent to bridges can deteriorate sooner so the team bolsters these areas with additional pavement depth.
Contractor paves deep pavement sections near bridge approaches. Roadways adjacent to bridges can deteriorate sooner so the team bolsters these areas with additional pavement depth.